Crown Hill started to expand onto the north side of Maple Road (now 38th Street) before the end of the 19th century. The construction of the Subway began in 1925.

This combination of bridge and underpass replaced a section of 38th Street at the center point of the northern edge of the cemetery’s South Grounds, allowing traffic to pass under the bridge to the new North Grounds without leaving the cemetery.

The Subway / Underpass

Facts

  • A. Bolen and Son, the firm responsible for the Gothic Chapel, designed the Subway/Underpass.
  • Edward Strathmann and Company built the structure.
  • The project was completed in 1927 at a cost of $170,000.